A substation next door is a useful lead. A service rating is useful evidence. Neither, by itself, establishes how much new load a utility will deliver to your project or when. A nationwide site search starts by asking what the power claim actually describes.

Define the load before comparing sites

Record required IT load and expected total facility demand separately. Describe the initial phase, expansion, operating date and reliability requirements. Ask whether quoted megawatts mean equipment rating, historical demand, requested utility service or committed delivery. Until the basis is clear, two identical numbers may describe very different opportunities.

The DOE data center design guide treats IT, cooling and electrical systems together. Our screening recommendation: have the project team establish the facility demand rather than applying an assumed conversion from utility megawatts to IT capacity.

What does each document establish?

This comparison is MegaScout's research framework, not a utility approval standard. Document wording and the applicable service process control. Keep each claim beside its issuer, parcel, date and unresolved question.

Evidence to request before relying on a powered-land claim
EvidenceWhat it can establishWhat it does not establish aloneNext check
Substation map or broker brochureA location or an attributed infrastructure claimSpare capacity, a reservation or a delivery dateIdentify the serving utility and request a parcel-specific assessment.
Bills and equipment recordsHistorical demand or installed equipment ratingsTransferable service or capacity for a different loadCheck active service, current obligations and the proposed load with the owner and utility.
Preliminary utility letterThe utility's stated assessment within its scopeUnconditional service unless the document actually commits itRecord the evaluated parcel, load, date, expiry and conditions.
Study resultsFindings for the scenario that was studiedCompleted upgrades or permission to energizeIdentify unresolved studies, required works and the applicable approval stage.
Executed service documentsObligations described in the applicable agreementsAutomatic transfer to another buyer or unrestricted expansionHave qualified advisers review parties, assignment, milestones and interruption terms.
Energization approval and operating recordsAn approval or actual operation within a documented scopeApproval for a larger or materially different projectConfirm the permitted load and requirements for the buyer's proposed changes.

Is a will-serve letter enough?

Read its scope before labeling a site power-ready. Does it specify the proposed customer, parcel, load and delivery schedule? Is it preliminary or conditional? What studies, agreements or works still stand between that letter and usable service?

Dominion Energy's Virginia data center team says it can provide preliminary power plans and will-serve letters during site selection. Its published connection steps include a site plan, load letter and load ramp schedule, followed by infrastructure design, rights of way, permitting and construction. That is a regional example of why the underlying delivery path matters; it is not a nationwide timeline or a commitment to a specific property.

Does a study approval mean the site can energize?

Identify the approval stage explicitly. A study finding, an agreement and authorization to energize are different evidence. Do not compress them into a single “approved power” label.

As checked October 1, 2026, ERCOT's Large Load Integration page publishes Batch Zero verification materials, including question guides dated September 18, 2026. It separately states that its new standalone large-load energization request must be submitted and approved before energization. The page also distinguishes its reference guides from controlling portal documents. For an ERCOT candidate, verify the current process and the project's actual stage with the relevant parties.

How should buyers compare time to power?

Ask for dated, phased delivery assumptions: initial service, expansion and full project demand. Record the dependencies behind each date and who is responsible for them. A seller's desired operating date belongs in a different field from a utility's documented milestone.

Illustrative comparison, not actual sites: Candidate A advertises a larger transformer rating but has no project-specific utility review. Candidate B has a smaller initial load addressed in dated utility correspondence, with later expansion still conditional. Neither is automatically preferable. Compare both with the buyer's initial load, expansion needs and required operating date; retain the open conditions in the shortlist.

Six questions for every power claim

  1. Who issued the number, on what date, and for which parcel and customer?
  2. Does it describe equipment capacity, past demand, requested service, committed facility load or IT load?
  3. Which initial and expansion phases were evaluated?
  4. What studies, upgrades, approvals, obligations and milestones remain?
  5. Is the arrangement firm or subject to interruption, curtailment or other conditions?
  6. Does it apply to this buyer and project, and what must be rechecked before relying on it?

For a former industrial site, add a seventh question: which service arrangements and equipment remain available after the previous operation ends? Historical usage is a research signal until current applicability is documented.

Compare markets without flattening the differences

Utility service processes and grid rules vary across the United States. PJM's August 13, 2026 announcement describes a proposed large-load framework. An announcement of a proposal does not establish its current regulatory disposition or service for a parcel. Check the applicable rule, tariff and project documents when evaluating a site.

A utility tariff can inform commercial research, but does not reserve capacity. Likewise, a generation project, power purchase proposal or nearby transmission line should not be treated as permission to connect a new data center load.

Turn uncertainty into a useful shortlist

Use separate fields for documented facts, attributed owner or broker claims, and unresolved questions. Record the research date, source, load basis, phase, delivery conditions and next verification action. Availability and owner willingness need their own evidence; a power document does not establish that a property is for sale.

MegaScout provides fee-based data center site selection research across all 50 states. We organize candidate evidence and next questions around your brief. Utility commitments, engineering acceptance and transaction diligence require the appropriate counterparties and professionals. Scope and fees are agreed before paid work starts.

Own a potential conversion site? Read the industrial property screening guide.

Research basis: the primary sources linked above were reviewed October 1, 2026. The comparison table and illustrative example are MegaScout's analysis. No site's power, availability or readiness is verified by this guide.