Three existing research candidates near MegaScout's Bloomsbury, New Jersey focus. This is a deeper desktop review, not a qualified shortlist. No owner, utility or professional feasibility confirmation has been obtained.
Three sites. Three different gates.
| Candidate | Decision |
|---|---|
| Allentown data center | Prioritize a document request |
| Hazleton industrial facility | Hold for land-use clarification |
| New Brunswick industrial property | Hold for control and use-path checks |
These are decisions about the next research step. No common buyer brief has been applied, and the findings do not establish available property, committed capacity or project feasibility.
Allentown data center
744 Roble Road, Allentown, Pennsylvania
Published evidence
Five 9s markets a 46,800 SF former data center with phased expansion. Its current announcement describes 11.1 MW in about 12 months and another 40 MW about 18 months after the first delivery. [S1]
The PDF also includes a 30-week second-phase statement, alongside an 18-month ramp. It labels existing power at 2.5 MW and N+1 UPS IT load at 849 kW. These are different metrics and broker claims. [S2]
What this changes
The evidence supports asking for current documents before making a schedule-based comparison. It does not support advertising the expansion as energized capacity or equating existing service with supported IT load.
Buyer fit to test
Potential fit for an existing-facility search if the buyer's initial IT load, location and delivery date match verified service and equipment. No common buyer brief has been applied.
Unresolved gates
- Current owner identity, exact parcels, offered rights and authority are not title-verified.
- No site-specific utility agreement, study, assignment terms or ramp schedule was obtained.
- Current equipment condition, occupancy, fiber service and development approvals remain unverified.
- No parcel-based flood, wetlands, environmental, airport-height or buildable-area clearance was performed.
Prioritized requests
- Ask the marketing broker for the dated, controlling utility schedule and reconcile every second-phase timing statement.
- Request utility service documents, delivered-versus-planned capacity, cost responsibility and conditions tied to each phase.
- Obtain equipment schedules, maintenance records and a load assessment separating service, UPS and critical IT capacity.
- Confirm legal owner, parcels, lease or sale terms, access authority and the municipality governing the parcel.
Hold or stop rule
Do not promote a committed power date until the utility evidence and applicable conditions support it. If the buyer requires earlier capacity than the verified path can deliver, hold or remove the candidate.
Next step: Broker document request first; utility and engineering review follow with owner authorization.
Hazleton industrial facility
533 Forest Road, Hazle Township, Pennsylvania
Published evidence
Colliers markets an industrial facility of approximately 185,959 SF on 18.17 acres. [S3]
The memorandum identifies PPL service but gives no parcel-specific MW. Its conceptual redevelopment is for industrial manufacturing/logistics; stated closing terms do not depend on redevelopment approvals. [S4]
Official June 8, 2026 minutes record adoption of Resolution 2026-16: a 180-day limited moratorium associated with a curative amendment addressing data centers and accessory uses. [S5]
What this changes
Industrial marketing and a utility name do not establish a data-center entitlement or capacity. The township action is a reason to obtain a current written land-use response; its specific effect on this parcel and any later changes remain unconfirmed.
Buyer fit to test
A conversion or redevelopment candidate only if a buyer can tolerate entitlement uncertainty and the eventual utility-service path. It should not be positioned as a near-term approved data-center site.
Unresolved gates
- The current ordinance, amendments and parcel-specific application path are not confirmed by the township.
- Owner title, exact parcel boundaries, occupancy and authority to pursue conversion remain unverified.
- No service rating, demand history, new-load allocation or utility delivery commitment was obtained.
- Environmental history, wetlands, flood exposure, ground conditions and usable area require parcel-based review.
Prioritized requests
- Request the adopted resolution, subsequent amendments and a current written zoning response for the proposed use at this exact parcel.
- Ask the seller's brokers to identify current occupancy, owner willingness, access rights and whether useful review can occur before a non-contingent closing.
- Obtain current service documents and a buyer-load-specific utility assessment; regional infrastructure descriptions do not answer this.
- Scope environmental and site/civil work after the use path is credible, before committing to acquisition.
Hold or stop rule
Keep on hold while the data-center use path is unresolved. Stop if the required approvals or delivery conditions conflict with the buyer's operating date or acquisition risk tolerance.
Next step: Township status request and broker control check first. Do not infer a blanket ban or an automatic approval.
New Brunswick industrial property
745 Joyce Kilmer Avenue, New Brunswick, New Jersey
Published evidence
Greiner-Maltz markets 138,000 SF on 10.7 acres, describes occupancy and vacant-delivery options, and reports 4,000 amps. Current whole-property availability is not owner-confirmed. [S6]
A historical Crexi flyer specifies 4,000 amps at 480 volts, three-phase. Separate divisible-lease marketing offers portions of the building. [S7] [S9]
The adopted 2025 Master Plan Re-examination recommends adding data centers as permitted uses in industrial zones. A recommendation is not evidence that the zoning ordinance was amended. [S8]
What this changes
Historical building-wide electrical figures cannot be assigned to a vacant suite or translated into buyer IT capacity without service and allocation documents. The use recommendation requires a check of current adopted regulations.
Buyer fit to test
Potentially relevant only for a buyer with a flexible conversion brief after confirming site control, contiguous space and the required use path. The historical electrical rating is not a basis for a capacity shortlist.
Unresolved gates
- Current ownership, rent roll, vacancies, parcel boundaries and offered control are not verified.
- Building-wide versus suite-specific service, meter allocations and equipment condition remain unknown.
- Current data-center land-use status, redevelopment overlays and permit requirements need a written municipal response.
- No parcel-level environmental, flood, wetlands, ground-condition or cooling/noise assessment was completed.
Prioritized requests
- Ask the broker to reconcile sale, vacant-delivery, sale-leaseback and divisible-lease materials with a dated availability schedule.
- Request a current rent roll, contiguous-space plan, meter map and owner authorization for a proposed change of use.
- Obtain service drawings and utility records identifying what belongs to each suite and what the proposed load would require.
- Ask city planning to identify the current ordinance and approval path for this parcel, rather than relying on the master-plan recommendation.
Hold or stop rule
Do not offer the whole building as available or label it data-center-ready. Hold or stop if control, contiguous area, tenant rights or the use path cannot support the buyer's project.
Next step: Current availability and planning checks precede utility or design spending.
Original sources
Marketing materials remain attributed claims. The municipal minutes and master plan establish what those documents record; a current parcel-specific response is still required.
- [S1] Five 9s Digital - Allentown announcement
- [S2] Five 9s Digital - Allentown marketing PDF
- [S3] Colliers - 533 Forest Road property page
- [S4] Colliers / CAN DO - Forest Road offering memorandum
- [S5] Hazle Township - June-August 2026 supervisors' minutes
- [S6] Greiner-Maltz - Joyce Kilmer property page
- [S7] Crexi - Joyce Kilmer historical flyer
- [S8] New Brunswick - adopted 2025 Master Plan Re-examination
- [S9] Showcase - Joyce Kilmer divisible lease marketing
Research boundaries
Define your search
Tell us your markets, initial and expansion IT load, property type, timing and the number of sites you expect to pursue over the next two years. Research scope and fees are agreed before paid work starts.